Q: Looks great!

I know the focus is heavy on personal goals. I miss one thing. Ghant chart. Rows for users, columns for time. Any chance you implement that in the future?

Founder Team
Tony_Upbase

Tony_Upbase

May 15, 2024

A: @creaktor,

Unfortunately, Gantt charts are not on the roadmap. We plan to add the timeline view only (no task dependency).

@Jack.S

Thank you for the answer!

Share
Helpful?
Log in to join the conversation
Jack.SPLUS

Gantt I don't know if it will be implemented.

https://upbase.canny.io/feature-requests/p/gantt-chart-with-dependencies

Timeline View is Planned❗

https://upbase.canny.io/feature-requests/p/timeline-view-for-tasks

🤔

Isn't it the same❓

The main difference between a timeline and a Gantt chart is that a timeline contains events visualized on a single line while a Gantt chart is a 2-dimensional chart of a sequence of tasks and their dependencies. Timelines give stakeholders a high-level overview of a project's start, end, and important milestones. Check cl1ck|_|p. If upbase ads dependencies, o boy!

Jack.SPLUS

@creaktor

Upbase does not yet have:

1) Milestones...
https://upbase.canny.io/feature-requests/p/milestones

2) Relationships between tasks (Task dependencies)
https://upbase.canny.io/feature-requests/p/task-dependencies

Therefore, currently Gantt could not be implemented.

Before this is possible, at least points 1) 2) must be implemented